RWE completes awards for three hydrogen-ready CCGTs involving Técnicas Reunidas

Ansaldo Energia will join two projects and GE Vernova the third, with Técnicas Reunidas handling design, construction and commissioning through TR Power.

Nora LindbergNovember 23, 20265 min read4 views
Concept illustration of three modern combined-cycle power plant complexes with hydrogen-ready equipment in an industrial landscape under soft dawn light.

RWE AG has completed the award of three hydrogen-ready combined-cycle gas power plants after receiving approval from the German government. Each plant is expected to have installed capacity of approximately 800–850 MW. The projects will be located at Weisweiler, Gersteinwerk and Voerde, all in North Rhine-Westphalia.

Consortia and construction scope

The first two plants will be developed by a consortium of Técnicas Reunidas S.A. and Ansaldo Energia S.p.A. The third will be developed by a consortium of Técnicas Reunidas and GE Vernova Inc. Técnicas Reunidas said its scope covers project design engineering, equipment supply, construction, commissioning and start-up.

Ansaldo Energia and GE Vernova will supply the gas turbines and steam turbines, along with their respective generators, heat recovery steam generators and other associated equipment. The division of work places overall project execution with Técnicas Reunidas while the turbine and major equipment packages come from the two technology suppliers.

TR Power as delivery platform

Técnicas Reunidas will carry out the three projects through TR Power, its subsidiary focused on combined-cycle power plants. The unit was established in January this year to pursue opportunities in the energy sector. The awards give the new subsidiary a role in delivering three large power-generation projects across multiple sites.

RWE’s positive auction results for the three hydrogen-ready CCGTs and its subsequent final investment decisions led Técnicas Reunidas to receive Notice to Proceed for the first contract. The company said the next notices would follow soon afterward and as planned.

Supply security and hydrogen readiness

Nikolaus Valerius, chief executive officer of RWE Generation SE, said the plants would make an important contribution to Germany’s security of supply by providing reliable, firm generation capacity when renewable power is not sufficiently available. He described construction as a major undertaking and said RWE was pleased to have Técnicas Reunidas as an experienced partner to deliver modern, hydrogen-ready plants.

Arturo Crossley, chief commercial officer of Técnicas Reunidas, said the awards strengthen the company’s position in Europe and support its commitment to power generation and the creation of TR Power. He said the company was proud to have contributed to RWE’s success in Germany’s first auction with a competitive, technologically advanced solution designed for a hydrogen future. According to Crossley, the solution will help the German electricity market secure flexible generation, enable greater renewable penetration, enhance security of supply and support decarbonization.

The projects are described as hydrogen-ready, meaning they are designed with future hydrogen use in mind; the announcement does not state operating hydrogen blends or commercial operation dates. The first contract has received Notice to Proceed, while the remaining contracts are expected to follow. For RWE, the three sites are intended to add firm capacity in North Rhine-Westphalia; for Técnicas Reunidas, the work is to be executed through TR Power.